NETIS - PUBLIC HOLIDAYS DATA PROCESS TIMETABLE 2006
Basic timescale as agreed NETIS WG Feb 04, with one week to Christmas lead in.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 8 weeks
| 16th Feb
| 16th Feb
| 2nd March
| 30th March
| 29th June
| 12th Oct
|
| Final details from operators
| |
|
| 6 weeks
| 2nd March
| 2nd March
| 16th March
| 13th April
| 13th July
| 26th Oct
|
| Data from source authorities for consolidation
| 4 weeks
| 16th March
| 16th March
| 30 March
| 27th April
| 27th July
| 16th Nov
|
|
| 3 weeks
| 23rd March
| 23rd March
| 6th April
| 4th May
| 3rd Aug
| 23rd Nov
|
|
|
|
|
|
|
|
| 18th Dec
|
Note # - 9 and 7 weeks for Christmas lead in, to provide extra time for anticipated extra scale of data work.
GH - Durham CC - 04/01/06
F:\PUBTRAN\PUBTRAN\INFO\NETIS\NETIS REPORTS\Public Hols Process\Public Hols Process Dates (06)